7 Coal Handling System
7.1 Basic Requirement
7.1.1 The design of coal handling system of a newly-built fossil fired power plant shall be planned comprehensively taking into account the construction scale of the current phase,planning capacity,coal type,coalconsumption,incomingcoaltransportationmode,unittype,localmeteorologicaland environmental conditions.It may be built either in phases or once for all.
7.1.2 The design of coal handling system of an extended fossil fired power plant shall make full use of the existing facilities and equipment and shall be in harmony with the existing systems.
推薦閱讀
- 架空輸電線路荷載規(guī)范
- GB50551-2010球團機械設(shè)備安裝工程質(zhì)量驗收規(guī)范(英文版)
- GB 50260-2013 電力設(shè)施抗震設(shè)計規(guī)范(英文版)
- DL/T 5546-2018 自然通風冷卻塔防腐設(shè)計導則
- 光伏支架結(jié)構(gòu)設(shè)計規(guī)程
- GB 50545-2010110kV~750kV架空輸電線路設(shè)計規(guī)范(英文版)
- DL/T 5505-2015 電力應(yīng)急通信設(shè)計技術(shù)規(guī)程
- GB 51284-2018 煙氣脫硫工藝設(shè)計規(guī)范
- DL/T5231-2010±800kV及以下直流輸電接地極施工及驗收規(guī)程(英文版)
- GB 51335-2018 聲屏障結(jié)構(gòu)技術(shù)標準
- DL/T 5516-2016 火力發(fā)電廠集中控制室及電子設(shè)備間布置設(shè)計規(guī)程
- GB 50588-2017 水泥工廠余熱發(fā)電設(shè)計標準
- DL/T 5501-2015 凍土地區(qū)架空輸電線路基礎(chǔ)設(shè)計技術(shù)規(guī)程
- DL/T 5153-2014 火力發(fā)電廠廠用電設(shè)計技術(shù)規(guī)程
- GB50397-2007冶金電氣設(shè)備工程安裝驗收規(guī)范(英文版)