6 General Arrangement of Main Power House
6.1 Basic Requirement
6.1.1 The general layout of the main power house shall be adaptable to the electric power production process,satisfy the requirements for installation,operation and maintenance and ensure that equipment layout is rational,space utilization is compact,the piping,wiring,and cabling is short,simple and neat,and the accesses for patrol inspection are unobstructed.
6.1.2 The areas in the main power house shall be arranged according to the functional requirements of the equipment and systems in a centralized and combined manner to attain definite function division and simple system connections.If the actual technical process and environmental conditions permit,the auxiliary equipment should be arranged outdoors or semi-outdoors.
6.1.3 The main power house may be arranged in three rows consisting of turbine house,coal bunker bay or combined deaerator and coal bunker bay,and boiler house,or in four rows consisting of turbine house,deaerator bay,coal bunker bay,and boiler house,or in other forms such as side coal bunker arrangement mode.
6.1.4 The arrangement of main power house shall provide favorable working environment for operation and maintenance personnel,comply with the applicable national labor protection codes currently in force;and the equipment arrangement shall meet the relevant requirements for protection against fire,explosion,damp,dust,corrosion,and freezing.
6.1.5 The color of facilities,panels,pipelines and platform staircases surrounding and within the main power house area shall be concordant.The platform staircases and railings should be of uniform sizes.
6.1.6 The column spacing in main power house should be uniform;and unequal column spacing can also be adopted provided that it can meet the arrangement requirements of the main equipment.
6.1.7 The arrangement of main power house shall be considered reasonably according to the plant area terrain,equipment characteristics and construction conditions.
6.1.8 The arrangement of main power house shall allow for further expansion according to the requirements of overall planning.
6.1.9 The arrangement of directly air-cooled system shall be in harmony with that of main power house,and shall comply with 17.8.4 herein.
- GB 50227-2017 并聯電容器裝置設計規范
- GB/T51075-2015選礦機械設備工程安裝規范(英文版)
- GB/T 50943-2015 海岸軟土地基堤壩工程技術規范
- GB50432-2007煉焦工藝設計規范(英文版)
- 電磁式流量傳感器測量方法及理論
- GB/T50663-2011核電廠工程水文技術規范(英文版)
- DL/T 5502-2015 串補站初步設計文件內容深度規定
- 機械基礎地基動力特性測試規程
- GB 51162-2016 重型結構和設備整體提升技術規范
- DL/T 5160-2015 電力工程巖土描述技術規程
- 汽車故障診斷技巧與禁忌速查手冊
- GB 50426-2016 印染工廠設計規范
- 冶金石灰焙燒工程設計標準
- 海上架空輸電線路設計技術規程
- GB 51170-2016 航空工業工程設計規范