5.4 Pipeline Arrangement
5.4.1 The thermodynamic pipes may be laid in the same pipe gallery and on the same pipe rack with the cement process pipes;in case any conflict occurs to the comprehensive layout of pipeline,the treatment mode shall meet the relevant requirements of the current national standard Code for design of general plan of industrial enterprises GB 50187.
5.4.2 In case underground pipelines are arranged within range of pavement,the method of direct burial or trench laying shall be determined by technical and economic comparison.
5.4.3 Overhead pipeline shall be arranged in accordance with the following requirements:
1 It shall use buildings(or structures)of cement production lines;
2 It shall not impede traffic,maintenance,natural lighting and natural ventilation of buildings,and shall ensure neat appearance;
3 Overhead lines should be arranged at corresponding position of underground pipelines.
5.4.4 The horizontal clear distance of underground pipelines,horizontal clear distance among underground pipelines,overhead pipelines and buildings(or structures),and vertical clear distance among underground pipelines and between underground pipelines and the intersections of railways and roads shall be determined by the engineering geology,framework foundation form,inspection shaft structure,burial depth of pipelines,pipe diameter,media inside pipes and other factors,and the minimum clear distances shall meet the relevant requirements of the current national standard Code for design of cement plant GB 50295.
5.4.5 Comprehensive layout of pipelines in renovation and extension projects shall not impede the normal use of existing pipelines.The distance among underground pipelines shall meet the relevant requirements of the current national standard Code for design of cement plant GB 50295.
- GB/T 50537-2017 油氣田工程測(cè)量標(biāo)準(zhǔn)
- GB50168-2006電氣裝置安裝工程電纜線路施工及驗(yàn)收規(guī)范(英文版)
- GB 50309-2017 工業(yè)爐砌筑工程質(zhì)量驗(yàn)收標(biāo)準(zhǔn)
- 真空電子器件生產(chǎn)線設(shè)備安裝技術(shù)標(biāo)準(zhǔn)
- GB 51134-2015 煤礦瓦斯發(fā)電工程設(shè)計(jì)規(guī)范
- GB/T 51266-2017 機(jī)械工廠年時(shí)基數(shù)設(shè)計(jì)標(biāo)準(zhǔn)
- GB/T 51132-2015 工業(yè)有色金屬管道工程施工及質(zhì)量驗(yàn)收規(guī)范
- 換流站接地極設(shè)計(jì)文件內(nèi)容深度規(guī)定
- GB/T 51250-2017 微電網(wǎng)接入配電網(wǎng)系統(tǒng)調(diào)試與驗(yàn)收規(guī)范
- DL/T5161.8-2002電氣裝置安裝工程質(zhì)量檢驗(yàn)及評(píng)定規(guī)程第8部分:盤、柜及二次回路接線施工質(zhì)量檢驗(yàn)(英文版)
- GB 51205-2016 精對(duì)苯二甲酸工廠設(shè)計(jì)規(guī)范
- 火力發(fā)電企業(yè)繼電保護(hù)技術(shù)監(jiān)督手冊(cè)
- DL/T5161.13-2002電氣裝置安裝工程質(zhì)量檢驗(yàn)及評(píng)定規(guī)程第13部分:電力變流設(shè)備施工質(zhì)量檢驗(yàn)(英文版)
- 信息技術(shù)標(biāo)準(zhǔn)化指南(第10版)
- GB/T 51259-2017 腈綸設(shè)備工程安裝與質(zhì)量驗(yàn)收規(guī)范