4.2 Thermodynamic System and Installation Scheme

4.2.1 The thermodynamic system shall be determined by the temperature and quantity of waste gas,and shall maximize the utilization ratio of waste heat.

4.2.2 Steam parameters of waste heat boiler shall be determined by the waste gas temperature and air flow volume,and parameters of thermodynamic system shall be determined by the factors,such as waste heat condition,turbine internal efficiency,etc..

4.2.3 One steam turbine unit may be used when utilizing waste heat of 2 cement production lines in the same plant.When the steam produced by the waste heat boiler of cement kiln with lower production is less than 30%of rated feed steam of the unit,2 steam turbine units should be used.2 or more steam turbine units should be used when utilizing waste heat of 3 or more cement production lines in the same plant.

主站蜘蛛池模板: 崇明县| 蒙山县| 拉萨市| 美姑县| 漳浦县| 安龙县| 新晃| 长治市| 武安市| 凤阳县| 嵊州市| 玉溪市| 临沭县| 吐鲁番市| 高尔夫| 琼海市| 蕲春县| 揭阳市| 千阳县| 南乐县| 饶平县| 丰原市| 杂多县| 佛学| 阿拉善右旗| 大田县| 郎溪县| 汶上县| 铜陵市| 获嘉县| 大化| 依安县| 红桥区| 探索| 太康县| 余姚市| 观塘区| 唐山市| 威信县| 新安县| 永福县|