4 Surveying and ROW Clearance
4.1 General Provision
4.1.1 Prior to construction,stake handover work shall be conducted.The contents of stake handover work shall include line control stake,temporary and permanent bench mark provided along the line.Stake handover record shall be signed for approval by representative of each party.
4.1.2 Obstructions shall be located accurately before surveying.Corresponding measures shall be taken to avoid obstructions during construction.
4.1.3 Survey personnel shall position the pipeline centerline and right-of-way limits.Each coordinate of pile shall be rechecked.
4.1.4 Construction contractor check and supervision unit repetition survey method shall be used for construction survey.
4.1.5 The allowable deviation of construction survey shall be compliance with Current national standard requirements of-“Code for Engineering Surveying”GB 50026.
4.1.6 After completion of pipeline erection,as-built survey shall be conducted.The actual survey value shall be indicated on original design drawings.The pipeline as-built drawing and single line diagram shall be drawn up.
4.1.7 After backfilling of pipe trench,the coordination controlling pile,and turning pile shall be recovered to original position.
- GB 50077-2017 鋼筋混凝土筒倉設計標準
- 配用電通信技術及產業發展報告
- 高素質應用型工程技術人才培養理論與實踐探索
- GB/T 50491-2018 鐵礦球團工程設計標準
- GB 51162-2016 重型結構和設備整體提升技術規范
- 建筑衛生陶瓷工廠節能設計標準
- DL/T 5505-2015 電力應急通信設計技術規程
- DL/T5231-2010±800kV及以下直流輸電接地極施工及驗收規程(英文版)
- GB50468-2008焊管工藝設計規范(英文版)
- DL/T5161.4-2002電氣裝置安裝工程質量檢驗及評定規程第4部分:母線裝置施工質量檢驗(英文版)
- 電力系統無功補償及調壓設計技術導則
- GB 50311-2016 綜合布線系統工程設計規范
- GB 51236-2017 民用機場航站樓設計防火規范
- 核電廠建構筑物維護及可靠性鑒定標準
- 林產加工工業職業安全衛生設計標準