4 Surveying and ROW Clearance
4.1 General Provision
4.1.1 Prior to construction,stake handover work shall be conducted.The contents of stake handover work shall include line control stake,temporary and permanent bench mark provided along the line.Stake handover record shall be signed for approval by representative of each party.
4.1.2 Obstructions shall be located accurately before surveying.Corresponding measures shall be taken to avoid obstructions during construction.
4.1.3 Survey personnel shall position the pipeline centerline and right-of-way limits.Each coordinate of pile shall be rechecked.
4.1.4 Construction contractor check and supervision unit repetition survey method shall be used for construction survey.
4.1.5 The allowable deviation of construction survey shall be compliance with Current national standard requirements of-“Code for Engineering Surveying”GB 50026.
4.1.6 After completion of pipeline erection,as-built survey shall be conducted.The actual survey value shall be indicated on original design drawings.The pipeline as-built drawing and single line diagram shall be drawn up.
4.1.7 After backfilling of pipe trench,the coordination controlling pile,and turning pile shall be recovered to original position.
- DL/T5161.10-2002電氣裝置安裝工程質量檢驗及評定規程第10部分:35kV及以下架空電力線路施工質量檢驗(英文版)
- GB/T 50554-2017 煤炭工業礦井工程建設項目設計文件編制標準
- GB 50309-2017 工業爐砌筑工程質量驗收標準
- GB/T50663-2011核電廠工程水文技術規范(英文版)
- 核電站鋼板混凝土結構技術標準
- 濕陷性土起始壓力測試規程
- 機械基礎地基動力特性測試規程
- GB50439-2015煉鋼工程設計規范(英文版)
- GB50402-2007燒結機械設備工程安裝驗收規范(英文版)
- GB 50404-2017 硬泡聚氨酯保溫防水工程技術規范
- DL/T 5516-2016 火力發電廠集中控制室及電子設備間布置設計規程
- DL/T 5543-2018 特高壓輸變電工程環境影響評價內容深度規定
- DL/T 5493-2014 電力工程基樁檢測技術規程
- GB/T 51280-2018 工程泥沙設計標準
- DL/T 5153-2014 火力發電廠廠用電設計技術規程