3.2 Material Mobilization
3.2.1 For material mobilization,the material plan shall be prepared in advance,and the material mobilization shall be organized according to the project scheduling.
3.2.2 The material shall be inspected and meet the following requirements prior to mobilization:
1 The ex-factory quality qualification documents of raw materials and standard elements shall be inspected,and their types,specifications and performance shall conform to the requirements of the design technical document or related current national product standards.
2 The quality of actual raw materials and standard elements shall be subject to random check of 1%of the materials(not less than 5 pieces)shall be checked per batch and type.In case re-inspection is specified in the design technical document or related current national standards,the re-inspection shall be performed as specified.
3 The unqualified raw materials and standard elements shall be timely removed from the site.
3.2.3 Upon mobilization,the raw materials and standard elements shall be free of defect,properly kept,and stored by category.
- 架空輸電線路荷載規范
- DL/T 5528-2017 輸變電工程結算審核報告編制導則
- DL/T 5390-2014 發電廠和變電站照明設計技術規定
- GB 51120-2015 通信局(站)防雷與接地工程驗收規范(英文版)
- GB/T 50770-2013 石油化工安全儀表系統設計規范(英文版)
- 滌綸工廠設計標準
- GB 51006-2014 石油化工建(構)筑物結構荷載規范(英文版)
- GB 51203-2016 高聳結構工程施工質量驗收規范
- GB/T 50436-2017 線材軋鋼工程設計標準
- GB 51284-2018 煙氣脫硫工藝設計規范
- 鐵路罐車清洗設施設計標準
- GB 50404-2017 硬泡聚氨酯保溫防水工程技術規范
- DL/T 866-2015 電流互感器和電壓互感器選擇及計算規程
- GB/T 50398-2018 無縫鋼管工程設計標準
- GB50754-2012擠壓鋼管工程設計規范(英文版)