1 General Provisions
1.0.1 This code is formulated with a view to ensure the installation quality of hard busbar,soft busbar,metal-enclosed busbar,gas-insulated and metal-enclosed busbar,insulator,metal ware,wall bushing and other devices,to promote the advancement of installation technology and to safeguard the operation of electric equipment.
1.0.2 This code is applicable to construction and acceptance of busbar equipment installation engineering at 750kV or lower.
1.0.3 The installation of busbar shall be carried out in accordance with the approved design documents.
1.0.4 The transportation and storage of equipment and apparatus shall be complied with the specification of this code.As products have other special requirements,they shall also be complied with the technical documents of these products.
1.0.5 The storage duration of equipment and apparatus prior to installation shall be less than one year.If longer duration is necessary,the requirements on storage of the equipment and apparatus shall be complied with the documents of the products.
1.0.6 The chosen equipment and apparatus shall be complied with to current relative national standards.Qualification certificate and nameplate shall be provided.
1.0.7 Inspection shall be carried out upon the equipments and apparatus arrival at the site.They shall be complied with the specification as the follows:
1 The packaging and sealing shall be well.
2 Inspection shall be carried with opening the package,and type and quantity of products shall be complied with design requirements,and accessories and spare parts shall be complete.
3 Technical documents shall be well.
4 Appearance shall be well.
1.0.8 Construction project shall be complied with specification of this code and current relative national standards for safety and technical standards and,the requirements of product technical documents.
1.0.9 Building engineering construction for busbar installation shall be complied with the following specifications:
1 The quality of buildings and structures related with busbar installation shall be complied with the current national standard GB 50300 Unified Standard for Constructional Quality Acceptance of Building Engineering.When there are other special requirements,it is also necessary to be complied with these requirements.
2 The building project shall be complied with the following requirements prior to the installation of busbar:
1)Foundation and structural frame shall be complied with design requirements for electric equipment.
2)Construction of roof and floor slabs shall be without any leakage.
3)Indoor floor construction has been completed.Screeding elevation shall be marked on the wall.
4)The foundation and structural frame shall be strong enough for electric equipment installation.The scaffold board,railings,stairs and platform of high-rise structure shall be complete and secure.
5)Decoration works that might damage or be obstructed by installed busbar shall have been finished.
6)The doors and windows have been installed.Construction road is unobstructed.
7)Reserved holes and pre-buried pieces for installing the busbar shall be complied with design requirements.
3 After busbar installation and before it is put into operation,the construction project shall be complied with the following requirements:
1)Pre-buried pieces,holes,expanded holes and other decorative works have been completed.
2)Protective nets,railings and all devices isolated from the energized parts shall be completed.
3)Iterms that will be obstructed by the energized equipment or will influence the safety of its operation shall been completed.
4)Construction facilities shall have been removed and the site shall have been cleaned.
1.0.10 The fasteners used for busbar shall be galvanized or stainless products shall be complied with current national standards.The outdoor tightening pieces shall be hot galvanized products.
1.0.11 The ceramic components for insulators and wall bushing shall be complied with current national standard GB/T 772 Technical Specifications of Porcelain Element for High Voltage Insulators and relevant specifications in this respect.
1.0.12 The structural metal parts and metal ware for fixing single phase AC busbar shall not form closed magnetic circuit.
1.0.13 In addition to this standard,the construction and acceptance of busbar device shall also be complied with other relevant current national standards.
- GB 51139-2015 纖維素纖維用漿粕工廠設(shè)計規(guī)范
- GB 51245-2017 工業(yè)建筑節(jié)能設(shè)計統(tǒng)一標(biāo)準(zhǔn)
- 電磁式流量傳感器測量方法及理論
- DL/T5161.6-2002電氣裝置安裝工程質(zhì)量檢驗(yàn)及評定規(guī)程第6部分:接地裝置施工質(zhì)量檢驗(yàn)(英文版)
- 石油化工廠際管道工程技術(shù)標(biāo)準(zhǔn)
- GB/T 50938-2013 石油化工鋼制低溫儲罐技術(shù)規(guī)范(英文版)
- GB 51237-2017 火工品試驗(yàn)室工程技術(shù)規(guī)范
- GB50217-2007電力工程電纜設(shè)計規(guī)范(英文版)
- GB51105-2015擠壓鋼管工程設(shè)備安裝與驗(yàn)收規(guī)范(英文版)
- DL 5068-2014 發(fā)電廠化學(xué)設(shè)計規(guī)范
- GB/T 50619-2010(英文版)火力發(fā)電廠海水淡化工程設(shè)計規(guī)范
- GB/T 51189-2016 火力發(fā)電廠海水淡化工程調(diào)試及驗(yàn)收規(guī)范
- GB 51151-2016 城市軌道交通公共安全防范系統(tǒng)工程技術(shù)規(guī)范
- GB50967-2014焦化機(jī)械設(shè)備安裝規(guī)范(英文版)
- 核電廠建構(gòu)筑物維護(hù)及可靠性鑒定標(biāo)準(zhǔn)