6.7 Arrangement of Flue Gas Denitration Facilities
6.7.1 The flue gas denitration facilities shall be arranged according to the following requirements:
1 The selective catalytic reduction(hereinafter referred to as SCR)should be arranged between economizer and air preheater.
2 The supports of SCR should be integrated with boiler framework to form a monolithic structure.
3 When it is required to reserve space for SCR,the space for SCR and its inlet and outlet flue ducts shall be reserved by fully taking into consideration the boiler framework and behind boiler arrangement and allowing for various resultant loads in relevant design.
4 The arrangement of non-selective catalytic reduction denitration reaction system and that of boiler shall be designed from an overall view.
6.7.2 The ammonia dilution system and urea decomposition system should be arranged close to denitration reactor.
- 鋼鐵企業原料場工程設計標準
- 設計系統發展研究
- GB 50227-2017 并聯電容器裝置設計規范
- GB/T 51183-2016 農業溫室結構荷載規范
- GB 51220-2017 生活垃圾衛生填埋場封場技術規范
- GB 51258-2017 玻璃纖維工廠設計標準
- 機械基礎地基動力特性測試規程
- GB 51237-2017 火工品試驗室工程技術規范
- GB 51184-2016 礦山提升井塔設計規范
- 建筑衛生陶瓷工廠節能設計標準
- 配電網規劃研究報告內容深度規定
- GB 51156-2015 液化天然氣接收站工程設計規范
- SH/T 3405-2012 石油化工鋼管尺寸系列(英文版)
- Rhinoceros三維產品建模及后期處理
- GB 51171-2016 通信線路工程驗收規范