6.5 Installation of Narrow Lap Welder
6.5.1 It is suitable to adopt the special tool to hoist the narrow lap welder,and when hoisting it,it is necessary to protect the pipeline and electric element on the equipment.
6.5.2 When adjusting the elevation and levelness,the upper surface of rail should be taken as the datum point.
6.5.3 The elevation of guide plate table should be 15mm-20mm lower than the passing-through line of strip.
6.5.4 When adjusting the longitudinal central line,the central line of base should be taken as the datum point.
6.5.5 When adjusting the lateral central line,the central line of movable frame should be taken as the datum point.
推薦閱讀
- DL/T 5528-2017 輸變電工程結算審核報告編制導則
- DL/T 5390-2014 發電廠和變電站照明設計技術規定
- 配用電通信技術及產業發展報告
- GB50172-2012電氣裝置安裝工程蓄電池施工及驗收規范(英文版)
- GB/T 51331-2018 煤焦化焦油加工工程設計標準
- GB50764-2012電廠動力管道設計規范(英文版)
- 平板玻璃工廠節能設計標準
- 鄭州軌道交通機電設備運營需求標準
- GB 51335-2018 聲屏障結構技術標準
- GB50473-2008鋼制儲罐地基基礎設計規范(英文版)
- GB/T 51273-2018 石油化工鋼制設備抗震鑒定標準
- Kubeflow學習指南:生產級機器學習系統實現
- GB 50390-2017 焦化機械設備安裝驗收規范
- GB 50421-2018 有色金屬礦山排土場設計標準
- 陽極炭塊堆垛機組安裝技術規程