6.13 Sealing Slide and Sealing Plate
6.13.1 Installation of sealing slide Figure 6.13.1 shall be based on the rail of sinter equipment,the tolerance of which shall be in accordance with the following requirements:
1 The elevation of sealing slide shall be adjusted,and checked by level and ruler with tolerance of±1.0mm;
2 The height differential between the corresponding points(a,a′)of two slides shall be adjusted,and checked by specific template rod and ruler with tolerance of±1.0mm;
3 The symmetrical longitudinal centerline of two slides shall be adjusted,and checked by wire/thread and ruler with tolerance of 2.0mm;
4 The transversal centerline shall be adjusted,and checked by wire/thread and ruler with tolerance of 2.0mm;
5 The center distance of slides shall be adjusted,and checked by wire/thread and ruler with tolerance of 2.0mm.

Figure 6.13.1 To survey elevation of sealing slide
1-Trolley rail;2-Sealing slide;3-Longitudinal centerline of sinter equipment;4-Template rod
6.13.2 Countersunk-headed screw of sealing slide shall be lower than the sliding surface of the slide.
6.13.3 The preset thermal expansion gap for seal slide shall be in accordance with the design document.
6.13.4 The plate movable sealing plate shall be installed as follows:
1 The longitudinal centerline shall be adjusted,and checked by wire/thread and ruler with tolerance of 2.0mm;
2 The transversal centerline shall be adjusted,and checked by wire/thread and ruler with tolerance of 2.0mm;
3 Gap between top surface of sealing plate and bottom surface of trolley of sintering equipment shall be adjusted,and checked by straight edge and ruler with tolerance of(2.0-3.0)mm.
6.13.5 Weight of counterbalance of plate movable sealing plate shall be adjusted until the upper part of sealing plate can move easily under specified load.Top surface of sealing plate shall be lower than the bottom surface of trolley,gap between two surface shall be(1.0-3.0)mm.
- GB 50349-2015 氣田集輸設(shè)計規(guī)范
- GB 51138-2015 尿素造粒塔工程施工及質(zhì)量驗收規(guī)范
- GB 51006-2014 石油化工建(構(gòu))筑物結(jié)構(gòu)荷載規(guī)范(英文版)
- DL/T5161.5-2002電氣裝置安裝工程質(zhì)量檢驗及評定規(guī)程第5部分:電纜線路施工質(zhì)量檢驗(英文版)
- GB/T 51243-2017 物聯(lián)網(wǎng)應(yīng)用支撐平臺工程技術(shù)標(biāo)準(zhǔn)
- 鄭州軌道交通機電設(shè)備運營需求標(biāo)準(zhǔn)
- GB/T 50436-2017 線材軋鋼工程設(shè)計標(biāo)準(zhǔn)
- 《電氣裝置安裝工程 低壓電器施工及驗收規(guī)范》實施指南
- 鄭州軌道交通安裝工藝運營需求標(biāo)準(zhǔn)
- DL/T 5543-2018 特高壓輸變電工程環(huán)境影響評價內(nèi)容深度規(guī)定
- 建設(shè)工程化學(xué)灌漿材料應(yīng)用技術(shù)標(biāo)準(zhǔn)
- 發(fā)光二極管生產(chǎn)工藝設(shè)備安裝工程施工及質(zhì)量驗收標(biāo)準(zhǔn)
- GB50742-2012煉鋼機械設(shè)備安裝規(guī)范(英文版)
- DL/T 5028.3-2015 電力工程制圖標(biāo)準(zhǔn) 第3部分:電氣、儀表與控制部分
- 建材工程術(shù)語標(biāo)準(zhǔn)