Sprint Planning  - part 2

The second part of Sprint Planning is for the Development Team to determine how they will do the work. Deciding how involves discussion and breaking down the work into tasks, for each Product Backlog item in the Sprint. At the end of the Sprint Planning Meeting, the resulting set of of work items, including the Sprint Goal is collectively known as the Sprint Backlog.

Once ready, the Sprint Backlog is added to the team's Scrum Board. For Scrum teams, this usually takes the form of physical board, such as a whiteboard or similar, and would look something like as follows: