3.2 Equipment Inspection
3.2.1 Equipment specifications,models and quantity shall meet the requirements of the procurement contract and design document.
3.2.2 Equipment packaging shall be complete,without signs of breakage,being damped or overheating and free of significant depressions.
3.2.3 All equipment shall be checked against the packing list and properly recorded.
3.2.4 After inspection,all equipment shall be stored in a classified manner and properly marked to indicate category and quantity.Special attention shall be paid to the storage of small components to prevent loss.
3.2.5 When inspection is completed,the inspection site shall be cleaned up and the inspection results shall be subject to the confirmation of the project owner or the project supervision engineer.
3.2.6 Factory test records of equipment shall be checked to make sure that they meet the requirements of procurement contract and design document.
- GB/T 51146-2015 硝化甘油生產(chǎn)廢水處理設(shè)施技術(shù)規(guī)范
- YS/T 5225-2016土工試驗規(guī)程
- GB 51120-2015 通信局(站)防雷與接地工程驗收規(guī)范(英文版)
- 焊接技能實訓(xùn)
- GB50542-2009石油化工廠區(qū)管線綜合技術(shù)規(guī)范(英文版)
- GB/T50663-2011核電廠工程水文技術(shù)規(guī)范(英文版)
- 強夯地基技術(shù)規(guī)程
- GB/T 50491-2018 鐵礦球團工程設(shè)計標準
- GB50580-2010連鑄工程設(shè)計規(guī)范(英文版)
- GB50629-2010板帶軋鋼工藝設(shè)計規(guī)范(英文版)
- 巖土工程勘察圖式圖例規(guī)程
- DL/T 866-2015 電流互感器和電壓互感器選擇及計算規(guī)程
- DL/T 5543-2018 特高壓輸變電工程環(huán)境影響評價內(nèi)容深度規(guī)定
- 變電站和換流站給水排水設(shè)計規(guī)程
- GB/T 51325-2018 煤焦化粗苯加工工程設(shè)計標準