6.6 Test Run
6.6.1 Check all parts running situation manually when perform the test run,and then carry out the automatic no load running.All equipments like the cylinder,pneumatic cylinder and electro-hydraulic cylinder back and forth run shall be not less than 5 times.
Inspection method:observation,check test run record.
6.6.2 Continuously run the shears shall be not less than 2 hours.There shall not have deformation and cracking at welding connection position.
Inspection method:observation,check test run record.
6.6.3 Test run the shear side lash adjusting mechanism not less than 5 times after received the cutting edge value.Accurately and evenly adjust the side lash.The cutting edge overlapping amount shall meet the requirements of design technical documents.
Inspection method:observation,check test run record.
6.6.4 Main motor brake braking times shall be not less than 5 times.The braking shall be stable and in accurate situation.
Inspection method:observation,check test run record.
- 中文版Rhino 5.0完全自學教程(培訓教材版)
- GB/T 51146-2015 硝化甘油生產廢水處理設施技術規范
- DL/T 5492-2014電力工程遙感調查技術規程
- GB 51177-2016 升船機設計規范
- DL/T 5491-2014 電力工程交流不間斷電源系統設計技術規程
- GB/T51050-2014鋼鐵企業能源計量和監測工程技術規范(英文版)
- GB/T 50770-2013 石油化工安全儀表系統設計規范(英文版)
- GB/T 50441-2016 石油化工設計能耗計算標準
- GB 50471-2018 煤礦瓦斯抽采工程設計標準
- GB50548-2010330kV-750kV架空輸電線路勘測規范(英文版)
- GB50071-2014小型水力發電站設計規范(英文版)
- DL/T5161.4-2002電氣裝置安裝工程質量檢驗及評定規程第4部分:母線裝置施工質量檢驗(英文版)
- GB50427-2015高爐煉鐵工程設計規范(英文版)
- DL/T 5493-2014 電力工程基樁檢測技術規程
- GB/T 51189-2016 火力發電廠海水淡化工程調試及驗收規范